Q: The proposal requests LCP, what if LCP is not provided?
A: The applicant is seeking the best possible price. If LCP is not provided, for whatever reason, or not submitted, the response shall not be disqualified, but the response may not score well based on the evaluation. Scoring for cost is calculated as a percentage. Low cost bidder divided by bid being evaluated gives an objective comparison of cost. Let me know if you have additional questions.